| has gloss | eng: Hitra Wind Farm is a 24 turbine wind farm located in Hitra, Norway and operated by Statkraft. Total installed effect is 24 x 2.3 MW. Maximum generated effect is 55 MW and total generating capacity is on average 150 GWh per year. The farm was opened on October 14, 2004. Until the expansion of Smøla Wind Farm in 2005, Hitra was the largest wind farm in the country and had total investments of NOK 450 million. |
| lexicalization | eng: Hitra Wind Farm |
| instance of | (noun) a turbine that is driven by the wind wind turbine |
| Meaning | |
|---|---|
| Norwegian | |
| has gloss | nor: Hitra vindpark ligger på Eldsfjellet på Hitra vel 300 meter over havet. Parken ble åpnet 14. oktober 2004 etter et drøyt års anleggsarbeid som startet i juli 2003. Det måtte bygges 20 km ny vei til anleggsområdet fra Straum, i tillegg til 10 km nye kraftlinjer. Investeringskostnaden for anlegget er vel 450 mill. kr. |
| lexicalization | nor: Hitra vindpark |